I. Basic Information on the Project, Including Its Name, Location, and Scope of Construction

Project Name: Intelligent Calcination Production Line Project for 170,000 Tons per Year of Prebaked Anodes at Shandong Pingyin Fengyuan Carbon Co., Ltd.

Construction Site: Kongcun Town, Pingyin County, Jinan City, Shandong Province

Main construction scope: Construction of one 66‑cell, 14‑bake‑box calcination furnace and associated environmental protection facilities at the new plant site. Upon completion, the project will have an annual production capacity of 170,000 tonnes of prebaked anodes.

Existing Facilities and Environmental Protection Measures: The existing facilities at the project site comprise a 180,000‑ton‑per‑year calcined coke production line, as approved in the “Environmental Impact Assessment Report for the Technical Renovation Project of the Prebaked Anode Production Line.” The environmental protection measures currently implemented by the existing project are as follows:

Waste gases: The flue gas from the calcination furnaces of the existing project is treated via SNCR–SCR denitrification, limestone–gypsum desulfurization, and a wet electrostatic precipitator integrated tower, then discharged through three 70‑m‑high chimneys (two in operation, one as backup). Particulate matter generated during the vibratory conveying of calcined coke is collected by baghouse filters and released through a single 33‑m‑high stack; particulate emissions from the discharge points within the calcined coke storage bins are likewise captured by baghouse filters and vented through three 41‑m‑high stacks.

Wastewater: Domestic wastewater from the existing project is treated in septic tanks and periodically removed.

Noise: Implement sound insulation and vibration reduction measures for equipment such as pumps, fans, and cooling towers.

Solid waste: Hazardous waste is entrusted to qualified entities for disposal; general solid waste is comprehensively utilized; and municipal solid waste is collected and transported by the sanitation authorities.

II. Name and Contact Information of the Project Owner

Construction Entity: Shandong Pingyin Fengyuan Carbon Co., Ltd.

Unit Address: Kongcun Town, Pingyin County, Jinan City, Shandong Province

Contact: Minister Liu

Contact number: 0531-58683675

III. Name of the Unit Preparing the Environmental Impact Report

Environmental Impact Assessment Agency: Shandong Haimeinong Project Consulting Co., Ltd.

IV. Online Link to the Public Opinion Form

The public opinion form for the environmental impact assessment of the construction project is attached.

V. Methods and Channels for Submitting Public Comments

During the preparation of the draft Environmental Impact Report, the public may submit comments related to the environmental impact assessment to the project proponent. The electronic version of the public comment form may be sent to the proponent’s email address (fytsaqhb@126.com), while the paper version may be submitted to the Safety and Environmental Protection Department of Shandong Pingyin Fengyuan Carbon Co., Ltd.

Attachment: Public Opinion Form for the Environmental Impact Assessment of a Construction Project

Shandong Pingyin Fengyuan Carbon Co., Ltd.

October 10, 2025